Market data · Corridors

Dwarka Expressway Toll Charges and Cost per km: 2026 Rates, CAG Report and Delhi-Gurgaon Toll History

By Aapt Dubey · Updated · 12 sources

From April 2026 a car pays ₹225 one way and ₹340 return at the Bijwasan plaza on Dwarka Expressway, and ₹100 one way at Kherki Daula on the Delhi-Gurgaon Expressway. Residents within 20 km can buy a ₹350 monthly pass. The CAG put the road's sanctioned civil cost at ₹7,287.29 crore, or ₹250.77 crore per km, against a ₹18.20 crore norm.

Dwarka Expressway Toll Charges and Cost per km: 2026 Rates, CAG Report and Delhi-Gurgaon Toll History: key figures infographic

Key figures

Car toll at Bijwasan, one way
₹225Dwarka Expressway, single journey for a car, after the 1 April 2026 revision; ₹340 for a returnSource 1
Car toll at Kherki Daula, one way
₹100Delhi-Gurgaon Expressway (NH-48), single journey for a car from 1 April 2026; ₹150 returnSource 1
Local resident monthly pass
₹350For residents within 20 km of the plaza, from April 2026; it was ₹340 when tolling began in November 2025Source 1
CAG cost per km
₹250.77 croreSanctioned civil cost per km in CAG Report No. 19 of 2023, against ₹18.20 crore per km approved by CCEA for the programmeSource 4
Sanctioned civil cost
₹7,287.29 croreFour NHAI packages approved January to March 2018, for 29.06 km in Haryana and DelhiSource 4
Awarded civil cost per km
₹181.94 croreMinistry of Road Transport and Highways reply to the CAG, August 2023; approved cost was ₹206.39 crore per kmSource 5
Official project cost
about ₹9,460 crore₹4,100 crore for the 19 km Haryana section plus ₹5,360 crore for the 10.1 km Delhi sectionSource 6
Traffic on NH-48, Delhi to Gurugram
3,11,041 vehicles a dayAverage daily traffic in the expressway's feasibility study, as cited by the CAGSource 4
Sirhaul toll share before removal
₹120 crore of ₹198 croreAnnual toll collected at Sirhaul versus the whole Delhi-Gurgaon Expressway, 2012-13Source 8

Dwarka Expressway toll charges in 2026

Dwarka Expressway stopped being free in November 2025, when NHAI began collecting at the new Bijwasan plaza near the Delhi-Haryana border. After the annual revision on 1 April 2026, a car pays ₹225 for a single trip and ₹340 for a return there. At Kherki Daula, the older plaza on the Delhi-Gurgaon Expressway, a car pays ₹100 one way and ₹150 return.

The two plazas are linked. The road ministry's rule, reported when tolling began, is that if you cross Bijwasan first you pay there and are not charged again at Kherki Daula on the same trip. If you cross Kherki Daula first, you pay the difference at Bijwasan. So a car driving the full corridor from Delhi into Gurugram and out past Kherki Daula pays the Bijwasan rate once, not both.

Regular users have two cheaper options. A 50-trip monthly pass costs ₹7,550 at Bijwasan and ₹3,320 at Kherki Daula. Residents within 20 km can get a local monthly pass for ₹350, up from ₹340 at launch, which works out to about ₹7 a trip and is why that number keeps appearing on social media. You need address proof matching the area and a FASTag linked to the vehicle. Commercial vehicles registered in the same district were reported to pay ₹50 a trip at Bijwasan from April 2026.

One-way car toll at Gurgaon's three main plazas, from April 2026(₹ per trip)
One-way car toll at Gurgaon's three main plazas, from April 2026
Bijwasan (Dwarka Expressway)225
Ghamdoj (Sohna Road)130
Kherki Daula (NH-48)100

Source: CMV360, 2026-04.

Car toll rates on the Delhi-Gurugram corridors from 1 April 2026
Toll plazaRoadOne wayReturnMonthly pass (50 trips)Local resident pass
BijwasanDwarka Expressway (NH-248BB)₹225₹340₹7,550₹350
Kherki DaulaDelhi-Gurgaon Expressway (NH-48)₹100₹150₹3,320₹350
GhamdojSohna Road₹130₹195Not reportedNot reported

Source: CMV360, 2026-04.

What do buses, trucks and commercial vehicles pay?

We could not verify the Bijwasan rates for light commercial vehicles, buses, trucks and multi-axle vehicles from NHAI's own fee notice, because NHAI's toll information site was not reachable when we checked in October 2026. Several property blogs publish a full vehicle-class table, but we do not reproduce rates we cannot trace to NHAI or a named news report.

What is on record: NHAI said overloaded vehicles would pay up to 10 times the normal toll, and the April 2026 report gives the ₹50 same-district rate for commercial vehicles at Bijwasan. For buses at Ghamdoj on Sohna Road, the same report gives ₹440 per crossing. If you run a fleet, check the plaza's posted rate board or NHAI's Rajmargyatra app before budgeting.

How Delhi-Gurgaon Expressway toll charges have changed

The car toll at Kherki Daula has gone up steadily. In March 2021 private cars paid ₹65 and NHAI approved ₹70 from 1 April 2021, under the terms of its contract with the concessionaire. By November 2025 the rate was ₹80 with no return-trip discount. When Bijwasan opened it rose to ₹95 one way with a ₹145 same-day return, and in April 2026 to ₹100 and ₹150.

This plaza has always been political. In 2021 a New Gurugram residents' group said over 20,000 families in Sectors 82 to 95 paid toll just to reach the rest of their own city, and the plaza handled some 75,000 vehicles on an average day. The CAG report notes that around 2017 a car paid ₹60 there.

One-way car toll at Kherki Daula(₹ per trip)
One-way car toll at Kherki Daula05010065Mar 202170Apr 202180Before Nov 202595100Apr 2026
One-way car toll at Kherki Daula
Mar 202165
Apr 202170
Before Nov 202580
Nov 202595
Apr 2026100

2021 values from The Tribune (1 April 2021); before-November-2025 and November 2025 values from The Tribune (22 November 2025); April 2026 value from CMV360. Years in between were not available to us. Source: CMV360, 2026-04.

Why the Sirhaul toll plaza was removed

Until February 2014 the Delhi-Gurgaon Expressway had three toll plazas: six lanes at IGI Airport, 18 lanes at Kherki Daula and 32 lanes at Sirhaul on the Delhi border. Sirhaul was the famous bottleneck, and it was also the money-maker. In 2012-13 it collected close to ₹120 crore of the ₹198 crore of toll taken on the expressway in a year.

After years of litigation and a settlement supervised by the Delhi High Court, the Sirhaul and IGI plazas were removed from the midnight of 20 February 2014. Lenders led by IDFC took over the 27.7 km road from the original concessionaire, and Kherki Daula became the only plaza, with the expectation that its rates would rise to make up the loss. The original build-operate-transfer concession, awarded in 2002, ran until 2023.

That history explains a point the CAG raised later. Moving the toll to Kherki Daula meant drivers between Delhi and Gurugram on NH-48 rode free for a decade. Linking Bijwasan and Kherki Daula into one tolled loop brings them back into the toll net.

Dwarka Expressway cost per km and the CAG report

The CAG's performance audit of Bharatmala Pariyojana Phase I, Report No. 19 of 2023, tabled in August 2023, is where the cost row started. It says NHAI approved four Dwarka Expressway packages between January and March 2018 with a civil cost of ₹7,287.29 crore for 29.06 km. That is ₹250.77 crore per km, against the ₹18.20 crore per km that the Cabinet Committee on Economic Affairs had approved for the national corridor programme it was built under.

The CAG's main objection was design. In Haryana, where the road runs 19 km, NHAI had a 90 metre right of way, which the CAG said was enough for a 14-lane road at ground level. NHAI instead built an eight-lane elevated carriageway over a six-lane road at grade. The CAG also said NHAI planned to buy back the Kherki Daula concession for an estimated ₹500 crore, adding to the cost.

The road ministry rejected the comparison. It said ₹18.20 crore per km was a normative figure for planning the programme, not an approved cost for each project, and that projects heavy with bridges, viaducts and tunnels averaged ₹152 crore per km. It put the approved civil cost of the four packages at ₹206.39 crore per km and the awarded cost at ₹181.94 crore per km, and pointed to a 3.8 km eight-lane tunnel and India's first four-level interchange. It also said building at grade would have cut the cost from ₹5,269 crore to ₹4,000 crore but produced a weaker road.

Dwarka Expressway civil cost per km, by measure(₹ crore per km)
Dwarka Expressway civil cost per km, by measure
CCEA programme norm18.2
Bharatmala average, bridge or tunnel heavy projects152
Awarded cost (MoRTH)181.94
Approved cost (MoRTH)206.39
Sanctioned cost (CAG)250.77

Ministry of Road Transport and Highways figures from its August 2023 reply; the ₹250.77 crore and ₹18.20 crore figures are from CAG Report No. 19 of 2023. All are civil construction costs, not total project cost. Source: India Infra Hub (Ministry of Road Transport and Highways statement), 2023-08.

Dwarka Expressway length, lanes and total cost

The official cost figures are higher than the CAG's civil cost because they cover the whole project. The Prime Minister's Office put the 19 km Haryana section at about ₹4,100 crore when it opened on 11 March 2024, and the 10.1 km Delhi section at about ₹5,360 crore when it opened on 17 August 2025. Together that is about 29.1 km and ₹9,460 crore, roughly ₹325 crore per km on our arithmetic.

A July 2020 government release had described a 30 km road costing over ₹8,000 crore. For lanes, the CAG describes the design as eight elevated lanes plus six at grade, 14 in all. Both are useful for a buyer: this is a heavy, grade-separated road, and it is now expensive to drive on unless you live close enough for the local pass.

Dwarka Expressway sections: length and cost (official figures)
SectionLengthCostOpened
Haryana: Delhi-Haryana border to Basai ROB10.2 kmPart of about ₹4,100 crore11 March 2024
Haryana: Basai ROB to Kherki Daula8.7 kmPart of about ₹4,100 crore11 March 2024
Delhi Package I: Shiv Murti to Dwarka Sector 21 RUB5.9 kmPart of about ₹5,360 crore17 August 2025
Delhi Package II: Sector 21 RUB to Delhi-Haryana border4.2 kmPart of about ₹5,360 crore17 August 2025
Whole expressway (our sum)about 29.1 kmabout ₹9,460 croreFully open August 2025

Source: Prime Minister's Office (pmindia.gov.in), 2024-03.

How much traffic was the road built for?

The feasibility study quoted by the CAG counted an average of 3,11,041 vehicles a day on NH-48 between Delhi and Gurugram, of which 2,88,391, or 92.72%, were passenger vehicles. Only 55,432 passenger vehicles a day (2018) went on past the Kherki Daula plaza. The other 2,32,959, about 80.78%, were local trips between Delhi and Gurugram.

That is the CAG's sharpest point: the eight elevated lanes serve longer-distance traffic, while the bigger local flow uses the six lanes at grade. For a resident of Sectors 99 to 113, it means the at-grade service road matters as much as the elevated deck. NHAI has also invited bids for barrier-free tolling on the expressway, which Nitin Gadkari told the Rajya Sabha about in December 2024; if it goes live, plaza queues should go but the charge will stay.

Frequently asked questions

From 1 April 2026 a car pays ₹225 one way and ₹340 return at the Bijwasan plaza. When tolling began in November 2025 the rates were ₹220 and ₹330. Kherki Daula charges ₹100 one way, but you do not pay both on the same trip.

Yes. A 50-trip monthly pass costs ₹7,550 at Bijwasan from April 2026. Residents within 20 km can get a local monthly pass for ₹350, which needs address proof and a FASTag linked to the vehicle.

No longer. It was free after the Haryana section opened in March 2024 and the Delhi section in August 2025, but NHAI started collecting at Bijwasan in November 2025.

A car pays ₹100 one way and ₹150 for a same-day return from 1 April 2026, up from ₹95 and ₹145 in November 2025. A 50-trip monthly pass costs ₹3,320 and the local resident pass ₹350.

CAG Report No. 19 of 2023 said the road's sanctioned civil cost was ₹7,287.29 crore for 29.06 km, or ₹250.77 crore per km, against ₹18.20 crore per km approved by CCEA for the programme. It questioned building eight elevated lanes when a 14-lane road at grade fitted the right of way.

Official figures put the 19 km Haryana section at about ₹4,100 crore and the 10.1 km Delhi section at about ₹5,360 crore, about ₹9,460 crore in total. The road ministry says the awarded civil cost was ₹181.94 crore per km.

The CAG describes it as eight elevated lanes plus a six-lane road at grade, 14 lanes in total. The ministry adds a 3.8 km eight-lane tunnel and India's first four-level interchange.

From the midnight of 20 February 2014, after a Delhi High Court supervised settlement. Sirhaul had 32 lanes and collected close to ₹120 crore of the expressway's ₹198 crore annual toll in 2012-13. Kherki Daula became the only plaza on the Delhi-Gurgaon Expressway.

How we compiled these figures

Toll rates for cars come from news reports of NHAI's November 2025 launch of the Bijwasan plaza (The Tribune) and the 1 April 2026 annual revision (CMV360); NHAI's own toll information site was not reachable from our location in October 2026, so we could not check its fee notices directly and have left out vehicle-class rates that we could not trace to a named source. Cost figures come from CAG Report No. 19 of 2023, the road ministry's August 2023 reply as reported by India Infra Hub, and Prime Minister's Office releases of March 2024 and August 2025. Total length and cost per km on official figures are our own arithmetic, and we say so where used. Toll rates change every April with the wholesale price index, so we review this page each quarter and after every revision.

Cite this page

Curated Homes, “Dwarka Expressway Toll Charges and Cost per km: 2026 Rates, CAG Report and Delhi-Gurgaon Toll History”, updated 15 October 2026, https://curatedhomes.in/stats/dwarka-expressway-toll-and-cost

You are welcome to use these figures and charts with a link back to this page.

Sources

  1. 1. CMV360, Delhi-Gurgaon Travel Cost Rises as NHAI Increases Toll from April 1 (2026-04-03). View source
  2. 2. The Tribune, Free travel ends on Dwarka Expressway, commuters to shell out Rs 220 one way (2025-11-22). View source
  3. 3. Outlook Money, Dwarka Expressway Toll Clarified: Real Rates, Local Pass Rules and the Rs 7 Calculation (2025-11-22). View source
  4. 4. Comptroller and Auditor General of India, Report No. 19 of 2023: Performance Audit on Implementation of Phase-I of Bharatmala Pariyojana (2023-08-10). View source
  5. 5. India Infra Hub (Ministry of Road Transport and Highways statement), Overall Outlay Provided, Civil Cost Varies On Nature Of Project: MoRTH Responds To CAG Report On Dwarka Expressway (2023-08-15). View source
  6. 6. Prime Minister's Office (pmindia.gov.in), PM to visit Haryana on 11th March (2024-03-10). View source
  7. 7. Prime Minister's Office (pmindia.gov.in), PM to inaugurate Rs 11,000 crore highway projects in Delhi on 17th August (2025-08-16). View source
  8. 8. Business Standard, IDFC could lose 60% revenue on Delhi-Gurgaon Expressway (2014-02-18). View source
  9. 9. Business Today (Mail Today), Delhi-Gurgaon toll plaza free after HC order (2014-02-20). View source
  10. 10. The Tribune, New Gurugram residents uproarious as Kherki Daula toll hikes toll charges (2021-04-01). View source
  11. 11. The Tribune, Bids called for barrier-free toll on Dwarka E-way: Gadkari (2024-12-05). View source
  12. 12. Press Information Bureau (Ministry of Road Transport and Highways), Projects in Haryana, July 2020 release (2020-07-14). View source
Free Buyer Consultation

Ready to find your dream home in Gurgaon?

Speak with Aapt Dubey, your RERA-compliant property consultant in Gurgaon. Free buyer consultation, legal & home-loan support, and verified listings.