Market data · Builders and RERA

Possession Delays in Gurgaon: Statistics, HARERA Orders and Delay Interest Rates

By Aapt Dubey · Updated · 12 sources

PropEquity's latest city count found 52,509 housing units in 158 stalled projects in Gurugram, 12% of the units it tracks in the city. A delayed buyer can claim interest at SBI's highest MCLR plus 2%, which is 10.95% a year from 15 October 2026, or a full refund with interest. HARERA Gurugram decided 5,024 complaints in 2025, but only 371 of 1,064 execution cases were disposed of in FY 2024-25.

Possession Delays in Gurgaon: Statistics, HARERA Orders and Delay Interest Rates: key figures infographic

Key figures

Stalled homes in Gurugram
52,509 units in 158 projectsPropEquity count of RERA-registered projects stalled, published August 2024; 12% of Gurugram's unitsSource: Hindustan Times
Delay interest rate from 15 Oct 2026
10.95% a yearSBI's highest MCLR (3 years, 8.95%) plus 2%, our calculation using SBI's published MCLRSource: State Bank of India
Rate applied in a September 2026 order
10.80% a yearHARERA Gurugram order of 29 September 2026 for 26 Kavyam buyers, Sector 108Source: The Tribune
Complaints registered and disposed, HARERA Gurugram
17,893 and 16,753Cumulative, per MoHUA RERA tracker cited by the authority in April 2026; 93.62% disposal rateSource: Hindustan Times
Old complaints cleared
2,174All complaints pending as of 31 March 2025, filed between 2018 and 2024, now disposed ofSource: The Tribune
Average time to decide
12 to 15 monthsHARERA Gurugram average disposal time, April 2026; target 6 to 9 monthsSource: The Tribune
Execution cases filed, FY 2024-25
1,064Cases filed to enforce HARERA orders; 371 disposed of in the same yearSource: Haryana Real Estate Regulatory Authority, Gu
Longest delay in 2024-25 report examples
About 7 yearsCentra One, Sector 61: due 31 December 2011, possession offered 19 November 2018Source: Haryana Real Estate Regulatory Authority, Gu
Gurugram projects restarted, 2018 to 2020
250Housing projects HARERA said it had helped restart in its first two yearsSource: Directorate of Information, Public Relations

What interest does a builder pay for delayed possession in Gurgaon?

Under the Haryana RERA rules, the builder pays interest at the State Bank of India's highest marginal cost of lending rate (MCLR) plus 2%. SBI's highest MCLR is its three-year rate. It rose from 8.80% to 8.95% on 15 October 2026, so orders passed from now on should use 10.95% a year.

You can see the rule in action in HARERA's orders. On 29 September 2026 the authority directed Agrante Realty to pay 26 Kavyam buyers 10.80% a year from the due date of 20 August 2023, The Tribune reported, and described that rate as SBI's highest MCLR plus 2%. Orders in HARERA's FY 2024-25 annual report use 11.10%, and the FY 2023-24 report shows 10.85% and 11.10%.

The same rate applies the other way. A buyer who pays late owes the builder the same interest, so keep your own payments on time if you plan to claim.

Figure 1: HARERA delay interest rate (SBI highest MCLR + 2%), start of each year(% a year)
HARERA delay interest rate (SBI highest MCLR + 2%), start of each year0102010.8Feb 2019Feb 2021Jan 2023Jan 202510.9Oct 2026
HARERA delay interest rate (SBI highest MCLR + 2%), start of each year
Feb 201910.75
Feb 202010.15
Feb 20219.3
Jan 20229.3
Jan 202310.6
Jan 202410.85
Jan 202511.1
Jan 202610.8
Oct 202610.95

Our calculation: SBI three-year MCLR from SBI's MCLR historical data plus 2 percentage points. Values match the rates used in HARERA orders where we could check them (10.75% in 2018-19, 10.85% and 11.10% in 2023-25, 10.80% in 2026). Source: State Bank of India, 2026-10.

How long are possession delays in Gurgaon?

The worst cases run to many years. In examples HARERA published in its FY 2024-25 annual report, a Centra One office unit in Sector 61 was due on 31 December 2011 and possession was offered on 19 November 2018, almost seven years late. In Neo Square, Sector 109, possession was due on 21 November 2013 and the occupation certificate came on 14 February 2019.

Affordable housing has its own share. Agrante's Kavyam in Sector 108 was due on 20 August 2023 under the 2013 affordable policy's four-year deadline. Before HARERA, the developer argued delivery should move to March 2026, citing about 129 days lost to GRAP construction bans; the authority kept the original due date.

Those are single cases. For the scale of the problem across the city, see the PropEquity and Anarock figures in the next section.

Delay examples from HARERA Gurugram orders
Project and sectorDue datePossession or OCDelayRemedy ordered
Centra One, Sector 61 (office)31 Dec 2011Offered 19 Nov 2018About 7 yearsRefund of ₹69.34 lakh with 11.10% interest
Neo Square, Sector 109 (commercial)21 Nov 2013OC 14 Feb 2019About 5 years 3 monthsDelay interest at 11.10% a year
Kavyam, Sector 108 (affordable)20 Aug 2023Interest runs until offer of possessionOver 3 years by the September 2026 orderDelay interest at 10.80% a year, 26 buyers

Source: Haryana Real Estate Regulatory Authority, Gurugram, 2026-04.

How many housing projects are stalled or delayed in Gurgaon and NCR?

PropEquity's last city-level count, published in August 2024, found 52,509 housing units in 158 stalled projects in Gurugram, 12% of the units it tracks in the city. Only Greater Noida (74,645 units, 17%) and Thane (57,520 units, 13%) were worse among the large cities. Nationally it counted about 5.08 lakh stalled units, up from about 4.65 lakh in 2018, in 1,981 projects across 14 tier I and 28 tier II cities (our sum of its two city groups). PropEquity blamed weak execution, cash-flow mismanagement and diversion of buyers' money into new land.

That count is now two years old and we have not found a newer Gurugram-specific figure from PropEquity or Anarock, so treat it as the latest published benchmark rather than today's number. Anarock's 2026 delivery data points the other way for NCR: only about 39,000 homes are scheduled for completion in NCR in 2026, out of 5,40,400 across the top seven cities. That small number reflects the 2021 to 2023 launch slowdown, not a clean bill of health.

History says schedules slip. Anarock notes that in 2020, 4.66 lakh homes were due for completion across the top seven cities and only 2.14 lakh, or 46%, were delivered. The buyer response in NCR has been a shift to national brands: Anarock says national developers' share of NCR launches rose from about 3% in 2022 to over 13% in 2025, and Gurugram took 47% of their NCR supply.

Figure 2: Stalled housing units by city (PropEquity, August 2024)(units)
Stalled housing units by city (PropEquity, August 2024)
Greater Noida74645
Thane57520
Gurugram52509
Bengaluru39908
Mumbai37883

Source: Hindustan Times (citing PropEquity), 2024-08.

Stalled housing units by city, PropEquity, August 2024
CityStalled unitsStalled projectsShare of city's units
Greater Noida74,64516717%
Thane57,52018613%
Gurugram52,50915812%
Bengaluru39,908225Not stated
Mumbai37,883234Not stated
All tracked cities (14 tier I, 28 tier II)about 5.08 lakh1,981 (our sum)Not stated

Source: Hindustan Times (citing PropEquity), 2024-08.

What can you claim if your flat is delayed?

Section 18 of the RERA Act gives you two choices. Stay in the project and claim interest for every month of delay until possession is offered, or withdraw and get your money back with interest from the date of each payment. HARERA's orders follow this pattern: in the Kavyam order, interest runs from the due date until offer of possession plus two months, arrears are payable within 90 days, and monthly interest is due by the 10th of each following month.

Compensation for mental harassment or loss is a separate claim before the Adjudicating Officer. That route is slower. In FY 2024-25 the Adjudicating Officer received 280 cases and disposed of 151, and total compensation awarded that year was ₹25.5 lakh.

In our experience, buyers who intend to take the flat usually do better claiming delay interest than a refund, especially when prices in the sector have risen since booking. If the builder is in financial trouble, the calculation changes and an early refund claim may be safer.

How fast does HARERA Gurugram decide delay complaints?

Around a year. The authority put its average disposal time at 12 to 15 months in April 2026 and said it wants that down to 6 to 9 months. It has cleared every complaint pending from 2018 to 2024, 2,174 in all, and decided 5,024 complaints in 2025.

Most of the backlog was recent. Of the 2,174 old cases, 1,060 were filed in 2024 and 654 in 2023, while only 15 dated from 2018.

On the cumulative count, the authority says it has registered 17,893 complaints and disposed of 16,753, a 93.62% disposal rate, citing the Ministry of Housing and Urban Affairs RERA tracker; it ranks third in India for complaints registered. In FY 2024-25 alone, 2,897 cases were filed before the authority and 3,033 disposed of, so it is now deciding more than it receives. Most orders in 2025 granted either a refund or delayed possession charges.

Figure 3: Old HARERA Gurugram complaints cleared, by year filed(complaints)
Old HARERA Gurugram complaints cleared, by year filed
201815
201928
202010
202174
2022333
2023654
20241060

Complaints pending as of 31 March 2025, all disposed of by April 2026, per The Tribune. Source: The Tribune, 2026-04.

Why do HARERA orders take so long to enforce?

Because winning is not the same as being paid. In FY 2024-25, 1,064 execution cases were filed with HARERA Gurugram and 371 were disposed of. In FY 2023-24 the figures were 1,023 filed and 294 disposed. Every year, far more buyers come back to enforce an order than get one enforced.

If the builder still does not pay, the matter goes for execution under Section 40 of the Act, and HARERA Gurugram runs a dedicated recovery cell. Before booking, check whether a developer has a long list of execution cases against it on the HARERA portal. It is a better warning sign than the number of complaints.

HARERA Gurugram execution cases
YearExecution cases filedDisposed of
FY 2023-241,023294
FY 2024-251,064371

Source: Haryana Real Estate Regulatory Authority, Gurugram, 2026-04.

How to check a Gurgaon project for delay risk before booking

Start with the HARERA registration page for the project. It shows the completion date the promoter declared, any extensions granted and the quarterly progress reports. A project that has asked for an extension, or whose reports have stopped, needs a hard look.

Next, search the authority's complaint and execution lists for the promoter's name, not just the project. Builders with delays elsewhere tend to repeat them. Then ask the bank: lenders that have approved a project have done their own checks, and a project no major bank will fund is telling you something.

Finally, read the possession clause in the agreement. HARERA counts delay from the due date written there, so a vague or very long grace period weakens your claim. If you would rather not take construction risk at all, a ready-to-move flat with an occupation certificate removes the question entirely.

What help exists for stalled projects?

At national level, HARERA Gurugram's FY 2024-25 annual report notes that the Union Cabinet approved a ₹25,000 crore alternative investment fund to revive around 1,600 stalled housing projects, and that Budget 2025 allotted ₹15,000 crore to the second phase of the SWAMIH fund for stalled affordable and mid-income projects.

Locally, HARERA said in February 2020 that it had helped restart 250 housing projects in its first two years, with construction continuing under its supervision, and its latest report says it inspects ongoing and stalled projects on site. If your project has stopped, file with other buyers rather than alone: a joint complaint with a common due date is heard together, as the 26 Kavyam complaints were.

Frequently asked questions

PropEquity's latest published count, from August 2024, is 52,509 units in 158 stalled projects in Gurugram, 12% of the city's tracked units. No newer Gurugram-specific count has been published by PropEquity or Anarock.

It says it has registered 17,893 complaints and disposed of 16,753, a 93.62% disposal rate, as of April 2026. In 2025 it decided 5,024 complaints, mostly granting refunds or delayed possession charges.

SBI's highest MCLR plus 2%. That was 10.80% for most of 2026 and becomes 10.95% for SBI's MCLR effective 15 October 2026.

Interest at the prescribed rate on the amount you have paid, for each month from the due date of possession until the builder offers possession plus two months, or actual handover if earlier. HARERA used exactly this formula in its September 2026 Kavyam order.

Yes. Under Section 18 you can withdraw and claim a refund with interest from the date of each payment. In one FY 2024-25 order HARERA directed a refund of ₹69.34 lakh with 11.10% interest for a unit delayed about seven years.

About 12 to 15 months on average as of April 2026. All complaints filed up to 2024 have been decided.

File an execution petition with HARERA. In FY 2024-25, 1,064 execution cases were filed and 371 disposed of, so enforcement takes time; unresolved matters are referred for execution under Section 40 of the Act.

Builders often claim it. In the Kavyam case the developer cited about 129 days lost to GRAP, but HARERA still held the due date of 20 August 2023 and ordered delay interest.

Yes, compensation is a separate claim before the Adjudicating Officer. It awarded ₹25.5 lakh in total in FY 2024-25 across the cases it decided.

How we compiled these figures

The delay interest rate series is our calculation from SBI's published MCLR history (three-year tenor, the highest) plus 2 percentage points, which is the rate the Haryana RERA rules prescribe; we checked it against rates used in HARERA orders. Case examples, filings and execution figures are from HARERA Gurugram's annual reports for FY 2023-24 and FY 2024-25. Backlog and cumulative complaint figures are from The Tribune's and Hindustan Times' April 2026 reports of the authority's statement. Stalled-unit counts are PropEquity's August 2024 city data (the latest Gurugram-specific count we found); 2026 completion schedules and the 2020 delivery shortfall are Anarock Research figures as reported by Hindustan Times and Forbes India. We update this page quarterly and whenever SBI changes its MCLR.

Cite this page

Curated Homes, “Possession Delays in Gurgaon: Statistics, HARERA Orders and Delay Interest Rates”, updated 15 October 2026, https://curatedhomes.in/stats/gurgaon-possession-delay-statistics

You are welcome to use these figures and charts with a link back to this page.

Update log

  • : First published.
  • : Added stalled-project counts and HARERA case data.

Sources

  1. 1. State Bank of India, Marginal Cost of Lending Rate and MCLR Historical Data (2026-10-15). View source
  2. 2. The Tribune, Gurugram HARERA directs builder to pay 10.8% delay interest to 26 Kavyam homebuyers (2026-10-14). View source
  3. 3. The Tribune, RERA Gurugram clears all pending cases till 2024, achieves 94% disposal rate among top in India (2026-04-08). View source
  4. 4. Haryana Real Estate Regulatory Authority, Gurugram, Annual Report FY 2024-2025 (2026-04-11). View source
  5. 5. Directorate of Information, Public Relations and Languages, Government of Haryana, HARERA Gurugram have resolved 70 percent complaints received in the last two years (2020-02-06). View source
  6. 6. Haryana Real Estate Regulatory Authority, Gurugram, Annual Report (Form ARA) FY 2023-2024 (2026-04-11). View source
  7. 7. Hindustan Times (citing PropEquity), Almost 5 lakh housing units stalled across 44 cities, Greater Noida tops the list: PropEquity (2024-08-15). View source
  8. 8. Hindustan Times (citing Anarock Research), US-Iran war could delay delivery of 5.4 lakh homes across India's top 7 cities in 2026: Anarock (2026-06-12). View source
  9. 9. Hindustan Times, Gurugram RERA disposes of all pending cases till 2024 (2026-04-09). View source
  10. 10. Forbes India (citing Anarock), West Asia crisis may impact delivery of 5 lakh homes in 2026 (2026-06-12). View source
  11. 11. The Times of India (citing Anarock Research), National realty giants tighten grip on NCR as local builders falter (2026-06-24). View source
  12. 12. Haryana Real Estate Regulatory Authority, Gurugram, Annual Report FY 2024-25 (cases filed and disposed of) (2026-04-11). View source